BRIDLE CALCULATOR
2-LEG BRIDLE · STATIC LOAD ANALYSIS
Angle: –
Angle: –
Static calculation for a stationary point load supported by two idealised tension-only legs. Anchor points are at the same elevation; angles are measured from the horizontal. Kilogram and pound values are converted to weight force using standard gravity (9.80665 m/s²). Self-weight, dynamic effects, connecting hardware and load capacities are not considered. The sum of leg tensions is not a resultant force. This calculation does not constitute a load capacity verification or replace approval by a qualified professional.
PYTHAGORAS CALCULATOR
RIGHT TRIANGLE · LENGTHS & ANGLES
Select two known values above. The selected inputs are editable; all remaining lengths and angles are calculated automatically. Angle γ is always 90°.
TRUSS LOAD CALCULATOR
2–10 PICKUPS · ELASTIC BEAM · TENSION-ONLY SUPPORT MODEL
Starting values: Prolyte H40V nominal self-weight 6.90 kg/m and illustrative EI = 2925.678 kN·m² (E assumed 70 GPa × Iy 4179.54 cm⁴). This EI is NOT the verified effective stiffness of an assembled truss. Enter a verified project-specific effective EI before relying on this beam model. Cable weight is uniformly distributed. Length-unit changes convert distances and kg/m or kg/ft; EI remains in kN·m².
Enter each pickup position and its relative attachment-height offset in millimetres. Positive offset = higher; negative = lower. Zero is the reference for all pickups; these are relative model coordinates, not chain-length measurements.
IMPORTANT DEFAULT ASSUMPTION: All height offsets start at 0 mm. This means the mathematical model assumes exactly equal pickup levels. In a real rig, such exact equality is difficult to achieve and cannot be inferred from the hoist settings alone. Even small height differences can change calculated load sharing. Entered offsets and EI must not be treated as verified measurements unless independently established.
The elastic FEM enforces vertical equilibrium, moment equilibrium, bending compatibility and tension-only contact. The model is conditional on the entered relative heights and effective EI. It does not determine real chain lengths, pretension, connection flexibility, torsion or structural capacity.
All reactions are in kg equivalents. They must balance total vertical force and moment. A successful check does NOT independently verify the source or truss capacity. Changing any position or load invalidates previously accepted values.
Enter suspended loads in kg and their positions from the left end in the selected length unit.
A pickup calculated as SLACK has 0 kg modelled tension only under the entered relative heights and beam EI. A different real hoist setting can redistribute load significantly. Results are model reactions, not measured hoist loads or verified capacities. No guessed weight allocations or replacement values are used.
IMPORTANT – CALCULATION LIMITATIONS: The displayed reactions come from an elastic Euler–Bernoulli beam finite-element model with linear bending, constant entered effective EI, vertical static point and distributed loads, rigid vertical pickup constraints at the entered relative height offsets, and tension-only (unilateral) contact. Forces, moments and support compatibility are checked independently before display. A pickup listed as SLACK is slack ONLY within these assumed constraints. Entering 0 mm everywhere imposes exactly equal relative pickup heights mathematically; this equality is difficult to reproduce or verify in a real rig, and these values are not measurements. A computed contact threshold or height required to engage a slack pickup is conditional on the assumed EI, loading and the fixed settings of all other pickups; it is NOT a real-world hoist adjustment instruction. The nominal Prolyte H40V EI default is an illustrative section-based assumption and is NOT verified for the assembled truss/joints. The model omits shear deformation, connection flexibility, hoist/chain elasticity, dynamic effects, horizontal/torsional loads, failure modes, capacities of truss/joints/roof/hoists and other rigging masses unless included as point or cable loads. Neither this calculation nor its PDF proves permissible load capacity or replaces a qualified structural assessment.